The method statement of ACP Cladding (Composite panel) method statement of personal roles and responsibilities during the installation. It including the scope of works to perform the site planning and preparation. And plan the personnel roles and responsibilities during the installation of ACP Cladding. 
Method Statement Cladding Installation

Scope of works During Cladding installation

This installation method statement serves to provide a guideline for carrying out the installation of Aluminum Composite Panel and its structural steel frame. The installation will include the following activities and sequences and may be changed to suit actual site conditions

 Site Planning and Preparation

  1.  Preparation of site office adjacent or near to the site as allocated by the Main Contractor.
  2.  Development of the storage area for materials required for the day to day works approximately 100m2 for external installations at the nearest possible locations where the installation is in progress.

The arrangement of safe access for facilitating installation of works.

  • Installation of steel bracket to support steel vertical frame runners.
  • Installation of steel vertical frame and horizontal runners.
  • Installation of Rockwool thermal insulation.
  • Installation of secondary weatherproofing barrier (EPDM) at roof cladding parapet. 
  • Installation of Aluminum Composite Panels.
  • The sealing of vertical and horizontal cladding joints by silicon sealants.

Personnel Roles and Responsibilities of installation team

Construction Manager:

He is overall in charge of ensuring that the formwork installation is carried out under this method statement.

 Zone Manager

He is in charge to ensure that adequate human resources, the required material, and the specified equipment are made available to the commencement of the works. He shall also ensure that proper access and sufficient lighting.

 Site Engineer:  

  1. The site engineer will make sure that the site preparation activities are conducted according to the approval Method Statement.
  2. It is the site supervisor’s responsibility to organize the work in a safe manner to ensure that safety and protective equipment are being properly utilized. He must also ensure that the safety requirements are implemented, and the approved method statement procedure is followed, and the ITP is, applied.

Project Manager

He shall oversee the overall performance of the project. He shall ensure adequate resources are variable for the execution of the works.
He is also responsible for ensuring effective implementation of the method statements.

Senior Supervisors

He shall coordinate the activities and provide technical support to the installation team.

Foreman and Supervisors

They are responsible for the control and implementation of the method statements.

Surveyors and the Installation Technicians

They are to follow the method statement related to their respective activities.

 QC Engineer

He is responsible for ensuring that inspection and test are carried as required.

Safety Team

He is responsible for checking that the appropriate measures are taken into account to ensure that the work is taking in a safe manner.

Project Manager and QA/QC Inspector

They will monitor, control and implement the Method Statement.

Document Controller

He will provide drawing from the Latest update during installation approved by the Technical Department Manager

QC Inspector and Material Coordinator

Materials delivered from the factory and from the supplier shall be checked by the QA/QC Inspector for conformance upon delivery at the project site, and material records shall be maintained by the Material Coordinator.

Contractor

The main Contractor shall provide access facilities and scaffolding to the installation team.

Senior Safety Officer

He shall monitor and ensure effective implementation of the health, safety, and environmental procedures/regulations.

Important Note

  • A company is to secure the necessary approval on the related design and shop drawing before the commencement of works on site.
  • The method statement will comply the approved design and shop drawings

COMMENTS

Name

Apps,34,Bahrain,1,Chrome,8,Construction,15,CorelDraw,1,Cydia,2,Devices,37,Du,1,Etisalat,1,Facebook,23,FB Web,16,Friendi,3,G Suite,14,GDrive,6,Gmail,27,Google,36,Hackintosh,6,Health,6,how,1,How To,171,Huawei,2,Iqama,71,Jazz,1,Lenovo,5,Linux,12,Messenger,10,Mobily,33,News,35,Qatar,9,Ramadan,8,Safety,17,Samsung,11,Saudi Arabia,234,SEO,5,STC,33,Tablets,1,Tech,52,Telenor,1,UAE,5,Ufone,1,Verizon,1,Virgin Mobile,1,Visa,25,Vodafone,1,Windows,27,WordPress,3,Zain,40,Zong,8,
ltr
item
HowGear: Cladding installation method statement responsibilities
Cladding installation method statement responsibilities
https://4.bp.blogspot.com/--vcfCi82bNw/WRxt8g47aUI/AAAAAAAAAi4/dRAlAgEWbRcQpCEGmhBx4HtYbQQ3fGPcgCK4B/s640/Method%2Bstatement%2Bcladding%2Binstallation.jpg
https://4.bp.blogspot.com/--vcfCi82bNw/WRxt8g47aUI/AAAAAAAAAi4/dRAlAgEWbRcQpCEGmhBx4HtYbQQ3fGPcgCK4B/s72-c/Method%2Bstatement%2Bcladding%2Binstallation.jpg
HowGear
https://www.howgear.com/2017/05/cladding-installation-method-statement.html
https://www.howgear.com/
https://www.howgear.com/
https://www.howgear.com/2017/05/cladding-installation-method-statement.html
true
3426953478503446100
UTF-8
Loaded All Posts Not found any posts VIEW ALL Readmore Reply Cancel reply Delete By Home PAGES POSTS View All RECOMMENDED FOR YOU LABEL ARCHIVE SEARCH ALL POSTS Not found any post match with your request Back Home Sunday Monday Tuesday Wednesday Thursday Friday Saturday Sun Mon Tue Wed Thu Fri Sat January February March April May June July August September October November December Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec just now 1 minute ago $$1$$ minutes ago 1 hour ago $$1$$ hours ago Yesterday $$1$$ days ago $$1$$ weeks ago more than 5 weeks ago Followers Follow THIS PREMIUM CONTENT IS LOCKED STEP 1: Share. STEP 2: Click the link you shared to unlock Copy All Code Select All Code All codes were copied to your clipboard Can not copy the codes / texts, please press [CTRL]+[C] (or CMD+C with Mac) to copy